The Education Ministry is preparing alternative arrangements, including rotating students on alternate days, for schools that may not be fully repaired by the start of the 2026/27 academic year in September.
This was disclosed by Parliamentary Secretary in the ministry, Senator Marlon Morgan, during a tour of several schools across St. Elizabeth on Monday.
The tour allowed for an assessment of reconstruction work being undertaken in the aftermath of Hurricane Melissa.
Senator Morgan said the ministry is working to ensure that as many schools as possible are fully restored for the start of the new academic year, while noting that some institutions may still have outstanding repairs when classes resume.
He indicated that where repair works are not fully completed, the ministry will have to implement practical measures to ensure that teaching and learning continue uninterrupted.
According to Senator Morgan, the ministry is mindful that ongoing construction while schools are in session can pose challenges, including noise and dust.
He said contractors are being urged to complete the work as quickly as possible while maintaining the required quality standards.
Among the works that Senator Morgan said have been delayed or remain outstanding are, roofing, window installation, and electrical.
Mr. Morgan cited contractor related challenges, adverse weather conditions, and shortages of critical building materials, among the contributing factors.