Rehabilitation of Cornwall Regional Hospital may be completed by September 2026, 5 months later than previous deadline

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

Checks being conducted to determine if more Cuban nationals landed in Jamaica illegally

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

Dennis Chung says first day as FID’s Chief Technical Director went well, ready to take on day two

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

It has nothing to do with ‘badmind’, it’s ‘goodminds’ standing against corruption – Golding calls for good governance

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

PNP condemns “inflammatory”, “reckless” comments by PM; says PNP protest today will be peaceful, principled and within bounds of law

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

PPV operators urged to exercise caution amidst counter-protests by JLP and PNP members over Dennis Chung’s FID appointment

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

Lobby group Stand Up for Jamaica suggests Bellevue Hospital be used to house and care for mentally ill inmates

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

FEATURE: Behind the Journalist’s Mask: Covering Tragedies

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

Police Commissioner declares the JCF will not return to a system where officers work in vacant roles without proper remuneration

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More

Mother charged after her 4 y/o child was fatally shot in Manchester last week

The rehabilitation of the Cornwall Regional Hospital in St. James is contractually scheduled to be completed by April next year, but the quantity of work being conducted may push that timeline to September 2026.

Consultant project manager for the rehabilitation of the facility, Vivian Gordon, gave the update during a tour by the Montego Bay Chamber of Commerce yesterday.

Mr. Gordon told reporters that the works are progressing well, but there are challenges to overcome.

He said some of those hurdles include the removal of a decommissioned underground storage tank, which housed bunker fuel to run the facility’s broiler.

He said medical and non-medical rehabilitative works are being conducted.

Meanwhile, First Vice President of the Montego Bay Chamber of Commerce Paulette Neil said the Chamber will keep the Ministry of Health and Wellness accountable as it relates to the projected completion timeline.

Read More